PDM Precast is submitting permits for a new 45,000 square foot production building at its Des Moines area campus in Carlisle, Iowa, the company said in a July 16, 2026 newsletter. The building will hold two relocated hollowcore beds, a new double tee bed, a new beam line, and new overhead cranes for stripping and material handling.

The expansion sits on newly acquired land the company calls Sunset Beach, bringing PDM’s total property in the area to roughly 50 acres. Along with the hollowcore and double tee equipment, the plan includes a relocated wall panel bed and a new short wall panel bed.

PDM’s steel division has also been busy this year, fabricating craneway columns weighing about 21,000 pounds each for a separate Robinson Inc. project in Altoona, Iowa completed between February and June.

makeprecast lists suppliers in its Cranes & Material Handling category.

Source: PDM Precast, July 2026.